(1) An entity which is laying, building, operating or expanding,
or which proposes to lay, build, operate or expand, a pipeline as a common carrier or contract carrier shall
apply in writing to the Board for obtaining an authorisation under this Act:
Provided that an entity laying, building, operating or expanding any pipeline as common carrier or
contract carrier authorised by the Central Government at any time before the appointed day shall furnish
the particulars of such activities to the Board within six months from the appointed day.
(2) An entity which is laying, building, operating or expanding, or which proposes to lay, build,
operate or expand, a city or local natural gas distribution network shall apply in writing for obtaining an
authorisation under this Act:
Provided that an entity laying, building, operating or expanding any city or local natural gas
distribution network authorised by the Central Government at any time before the appointed day shall
furnish the particulars of such activities to the Board within six months from the appointed day.
(3) Every application under sub-section (1) or sub-section (2) shall be made in such form and in such
manner and shall be accompanied with such fee as the Board may, by regulations, specify.
(4) Subject to the provisions of this Act and consistent with the norms and policy guidelines laid
down by the Central Government, the Board may either reject or accept an application made to it, subject
to such amendments or conditions, if any, as it may think fit.
(5) In the case of refusal or conditional acceptance of an application, the Board shall record in
writing the grounds for such rejection or conditional acceptance, as the case may be.