Section 33:
Order of demolition of buildings in certain cases.
19
(1) Where the erection of any building
has been commenced, or is being carried out, or has been completed, in contravention of any restriction or
condition imposed under sub-section (7) of section 10 or a plan for the re-development of any clearance
area or in contravention of any notice, order or direction issued or given under this Act the competent
authority may, in addition to any other remedy that may be resorted to under this Act or under any other
law, make an order directing that such erection shall be demolished by the owner thereof within such time
not exceeding two months as may be specified in the order, and on the failure of the owner to comply
with the order, the competent authority may itself cause the erection to be demolished and the expenses of
such demolition shall be recoverable from the owner as arrears of land revenue:
Provided that no such order shall be made unless the owner has been given a reasonable opportunity
of being heard.
20
(2) For the purpose of causing any building to be demolished under sub-section (1), the competent
authority may use or cause to be used such force as may be necessary.
Notes:
19. Section 33 renumbered as sub-section (1) thereof by s. 17, ibid. (w.e.f. 27-2-1965).
20. Ins. by s. 17, ibid. (w.e.f. 27-2-1965).