Section 4E:
Inspection during erection.
1[4E. Inspection during erection.--(1) The owner who proposes to register a boiler under section
7, shall engage on Inspecting Authority for carrying out inspection at the stage of erection of the
boiler.
(2) The Inspecting Authority shall follow such procedure for inspection and certification of a
boiler or boiler component, or both as may be prescribed by regulations and after inspection if it is--
(a) satisfied that the erection of the boiler is in accordance with the regulations, it shall issue a
certificate of inspection in such form as may be prescribed by regulations; or
(b) of the opinion that the boiler has not been erected in accordance with the regulations, it
may for reasons to be recorded in writing, refuse to grant the certificate and shall communicate
such refusal to the manufacturer of the boiler or boiler component forthwith:
Provided that no such certificate shall be refused unless the Inspecting Authority had directed
the owner in writing to carry out such modifications or rectifications as it deems necessary and the
Inspecting Authority is of the opinion that in spite of such direction the owner did not carry out
the direction.
(3) The Inspecting Authority may, for the purposes of inspection under this section, charge such
fee as may be prescribed by regulations.]