Long Title: An Act to consolidate and amend the laws relating to reorganisation and insolvency resolution of corporate persons, partnership firms and individuals in a time bound manner for maximisation of value of assets of such persons, to promote entrepreneurship, availability of credit and balance the interests of all the stakeholders including alteration in the order of priority of payment of Government dues and to establish an Insolvency and Bankruptcy Board of India, and for matters connected therewith or incidental thereto.

Ministry: Ministry of Corporate Affairs

Department:

Section 54D: Time-limit for completion of pre-packaged insolvency resolution process
     54D. Time-limit for completion of pre-packaged insolvency resolution process.--(1) The prepackaged insolvency resolution process shall be completed within a period of one hundred and twenty days from the pre-packaged insolvency commencement date.
    (2) Without prejudice to sub-section (1), the resolution professional shall submit the resolution plan, as approved by the committee of creditors, to the Adjudicating Authority under sub-section (4) or sub-section (12), as the case may be, of section 54K, within a period of ninety days from the prepackaged insolvency commencement date.
    (3) Where no resolution plan is approved by the committee of creditors within the time period referred to in sub-section (2), the resolution professional shall, on the day after the expiry of such time period, file an application with the Adjudicating Authority for termination of the pre-packaged insolvency resolution process in such form and manner as may be specified.